Exclusive: Interstate connector the spark for fourth industrial revolution

Exclusive: Interstate connector the spark for fourth industrial revolution

Wed, 25th Nov 2026 (Today)
Mike Bishara
MIKE BISHARA Features Editor

Project EnergyConnect (PEC) is not flashy, or even very well known to mainstream Australia, but it is a A$3.6 billion catalyst, hoping to model the beginning of the end for fossil-fuel dependence, and offer the promise (eventually) of cheaper electricity costs for consumers in Australia.

PEC is Australia's largest electricity transmission interconnector, adding 800 megawatts (MW) of transfer capacity in a 900-kilometer high-voltage power line linking the energy grids of New South Wales (NSW), South Australia and Victoria.

With up to 80 percent of NSW's coal-fired power stations scheduled to retire by 2033, the PEC link will progressively increase its operational capability into 2027, unlocking wholesale electricity sharing and supporting the retirement of coal-fired power stations.

In addition, the three-state transmission loop adds critical redundancy. If one state faces extreme weather or a generator outage, electricity can quickly flow in from neighbouring states to prevent blackouts. 

Many see it as Australia's first meaningful strike in keeping pace with Industrial Revolution 4.0 - defined as artificial intelligence (AI), internet of things, robotics, 3D printing and cyber-physical systems. 

AI needs copious quantities of electricity from data centers, which an innovative Australia plans to provide from renewable energy zones (REZ).

What Project EnergyConnect does

Jointly delivered by Transgrid and ElectraNet, the project creates the first transmission loop in Australia's National Electricity Market (NEM). 

Primarily, it will support demand for a stable electricity supply to drive the growth of data centers for artificial intelligence (AI), without destroying the planet to do it.

The Project EnergyConnect line unlocks major REZ, allowing large-scale wind, solar, and battery storage projects across regional South Australia and southwestern NSW to be developed and be fed directly into the national grid.

AI development is driven by the power of data centers and neither is going away any time soon, like it or not. Implementation can be delayed by public protest and partisan politics but, ultimately, it cannot be derailed.

Two thirds of Australia's existing data market centers are grouped around Sydney NSW (56), Melbourne Victoria (34) and Adelaide South Australia (10), a number which will grow exponentially in the next decade.

Hyperscale data centers belong in a REZ

AI has accelerated the rise of "hyperscale" data centers. A typical large facility can demand 100MW of power - equivalent to the consumption of about 100,000 homes. 

Because clean renewable energy cannot yet provide steady, 24/7 power on demand everywhere, many data center developers still rely on natural gas or even plan on-site fossil-fuel generators, which threatens to spike carbon emissions.

Cheaper power bills but there's a catch

The massive infrastructure costs and localized demand spikes from clustered data centers are contributing to rising electricity costs. 

The hope for cheaper power bills is premised on the theory that sharing surplus renewable power among three states will reduce wholesale price spikes and narrow price gaps between regions. 

Project modelling estimates that typical residential bills in South Australia, for example, will drop by about $100 per year, while NSW customers will save around $180 million annually. 

That politically fashionable pitch is substantially true but is more of a welcome side-effect to the prime purpose of PEC and the development of REZ. 

Can we save the planet and cut electricity costs at the same time

The catch is that Transgrid, with joint partner Electranet, has applied to the Australian Energy Regulator to recover a portion of the project's budget blowouts of more than $1.1 billion from consumers through their power bills. 

The bill has to be paid but where it will come from depends on whether or not a federal or state government is brave enough to load it on to already beleaguered consumers while trying to sell them on the notion of how much they are saving the planet.

The real aim of PECs models across Australia

PEC's job also is to help drive artificial intelligence training centers to rural REZ and provide a working model for the country.

AI training centers (aka AI data centers, campuses or factories) are specialized physical facilities built to house the massive computing hardware needed to develop and teach artificial intelligence models. 

These facilities are engineered to process vast amounts of data simultaneously so AI systems can learn patterns and make decisions.

The massive infrastructure costs and localized demand spikes from clustered data centers have already begun to spill over, contributing to rising electricity costs for residential and commercial customers nearby. 

Training an AI model requires massive electricity. A single server rack in an AI facility can draw 60kW to more than 120kW of power, compared to just between 5kW and 10kW in a standard data center.

Good outcome from an unpopular cause

The PEC line runs from Robertstown in South Australia to Wagga Wagga in New South Wales, with a key hub in Buronga and an added spur into Red Cliffs in northwestern Victoria.

PEC includes more than 1400 new transmission towers, new and upgraded substations and Australia's first 500kV transmission line built in more than 30 years. 

The win-win is that PEC unlocks access to new major REZ, allowing the further development of large-scale wind, solar and battery storage projects across regional South Australia and south-west NSW which will feed directly into the national grid.

There are no hyperscale data centers currently operating directly along the rural transmission route. Likewise, there is no official public tally of every data center accessible to the PEC transmission line, largely because early-stage grid connection applications are commercially sensitive. 

Also, the line currently serves the broader inter-connected NEM rather than acting as a dedicated data center spur.

Interest builds for proposed data center projects

Transmission owner ElectraNet has received 30 early-stage data center proposals across the state. Only five have been officially announced and most still require a separate $5 billion internal South Australia grid upgrade to connect.

The most prominent project directly tied to PEC is IREN's proposed 800 MW AI data center at the South Australian entry point, with first energisation targeted for 2028. 

With construction completed and full energisation underway by Transgrid, Project EnergyConnect moves into testing, cost recovery and grid integration phases.

The Australian Energy Market Operator (AEMO) is scheduled to conduct inter-network testing throughout late 2026 to ensure the interconnector safely stabilizes power flows between the three states.

Capacity is being released in stages up to its full 800MW bi-directional limit, with full commissioning expected by late 2027. 

AEMO says it plans also to operate the South Australia power system "some time" in the future without any synchronous generators (rotating electrical machines that convert mechanical energy into alternating current electrical energy.) 

South Australia would be relying on synchronous condensers, renewables and batteries to maintain the power system under normal conditions. AEMO says. "The interconnectors would help supply diversity and power system stability." 

Laying a foundation for the future

Accepting that data centers and AI need electricity and plenty of it, Australia could have facilitated their development by expanding the use of its massive reserves of fossil fuel, primarily coal in this instance. 

It has chosen instead to exploit the inevitability of AI by producing a model that cleverly embraces the need for climate change on the supply side with REZ with the demand for economic innovation through data centers and AI. 

Tightening up the rules for in-city construction.

The development of REZ is actively driving at least a partial decentralization of data centers away from Sydney and Melbourne. 

While latency-sensitive workloads must stay close to major populations, energy-hungry AI training facilities are increasingly moving to regional hubs and REZ corridors where land and green power are abundant. 

Latency sensitivity refers to the degree to which an application or workload's performance is affected by longer-than-usual requests and response cycle times.

Cloud computing, financial trading, enterprise IT, and AI inference (delivering real-time answers to users) still require proximity to major population centers and subsea cable landing stations in Sydney, Melbourne and Perth.

There's nothing more precious than water

Many inland REZ are being located in dry agricultural regions where securing water for evaporative cooling is politically and environmentally sensitive, forcing operators to adopt more expensive closed-loop or air-cooled systems. 

Even with this drawback, the major plus is that large-scale AI model training does not require ultra-low millisecond latency to end-users. This makes regional REZs commercially viable for hyperscale AI campuses. 

Planning is underway for related and subsequent major infrastructure upgrades, such as the South West Renewable Energy Zone extensions, HumeLink (connecting to Snowy 2.0) and VNI West.

Data centers now account for 2.8 percent of the electricity consumption on Australia's east coast and are expected to consume more than 10 percent by the mid-2030s. 

Getting ready for new players

State and federal policy reforms now mandate that large new data centers match their consumption with new renewable generation and storage. 

Building directly inside or near REZs allows operators to co-locate with wind, solar and battery projects rather than paying massive network upgrade fees in congested city grids. 

Metropolitan hubs like Western Sydney and Melbourne's west already face severe transmission congestion, strict zoning buffers and intense water constraints. 

Still, such is the urgency to accommodate AI there are plans to build on a 52-hectare site one of the biggest data centers in the world at Kemps Creek, Western Sydney. If it goes ahead, it will include six four-storey buildings alongside 936 cooling units and 852 diesel backup power generators.

By contrast, regional areas offer cheap, expansive land parcels needed for gigawatt-scale AI campuses. REZ infrastructure builds out high-voltage transmission lines linking regional generation to state grids and corridors such as PEC. 

Positioning data centers along these corridors such as PEC and Gippsland or regional NSW taps into bulk power before it hits urban bottlenecks. 

Leveraging legacy coal-power transmission infrastructure in Victoria's Latrobe alongside offshore wind and REZ developments, for example, is expected to attract multi-billion-dollar projects.

In regional NSW there is expanding edge and hyperscale interest across corridors tied to the Central-West Orana, Hunter and New England REZ.

A positive model for the country to follow

PEC is a start to strengthen power reliability for current and planned data-center pipelines and could well be the base model for an Australian future of equitable energy infrastructure fuelled by renewable sources.

AEMO has registered 11 large-scale transmission-level projects (totalling 5.4 GW) actively moving through the formal connection process in 2026.

Many more sit in earlier planning stages across NSW and Victoria, though analysts say only a fraction of total gigawatts requested nationwide will be built because of local network bottlenecks and community opposition.