Story image

How data center pod frames can shorten IT room deployment time by over 20%

16 Oct 17

Every day your data center isn’t operational is another day you’re not generating revenue or getting that critical business application online.

If you’re a colocation data center, not having the IT space ready can mean the difference of getting that new client or not…

While there is quite a bit of variation from one project to the next, in many data centers today, you find ceiling grid systems used to support and distribute cables throughout the IT space, you see raised floors filled with power and/or network cables, blocking airflow, and you see containment systems mounted directly to IT racks (if they have containment at all). 

These practices have a number of negative impacts to cost, flexibility, and efficiency, but in this blog, I want to focus on their implications to the project timeline, and discuss an alternate approach to accelerate the deployment time.

My colleague, Patrick Donovan, & I recently published a white paper, Analysis of How Data Center Pod Frames Reduce Cost and Accelerate IT Rack Deployments, to discuss, among other things, how this project time line can be reduced by over 20% using free standing pod frames (that are independent of the IT racks) - an approach that reduces much of the construction work, and makes it more of an assembly project.

In the paper, we analyze a 1.3MW data center, and compare two IT room deployments:

Traditional approach 

Network cabling distributed overhead on ceiling grid structure/ladders, power distributed from RPPs under the raised floor to each rack, containment mounted to the IT racks

Pod-frame approach 

Network and power distributed on support cantilevers on the pod frames; containment mounted to the pod frames

Schedulers from Schneider Electric’s design build services team created project timelines and Gantt charts for the two alternatives.

While many of the steps remain unchanged for the installation of these two IT rooms, there were some key differences that ultimately resulted in 21% savings.

This included:

  • Reduced ceiling grid work: No ceiling grid was needed directly over each IT pod, so the time to install the Unistrut grid system was reduced from 8 days down to 4 days.
  • Eliminated under-floor cable trays and cutouts: We assumed a raised floor in both scenarios, but in the traditional design, the added steps of installing under-floor cable trays, making cutouts in the tiles for the cables, and placing grommets and brush-strips in the cutouts are necessary. This added 7 days of labor.
  • Faster installation of power whips: Running power whips from panels over ladders on cantilevers (on the pod frame) to the IT racks is simpler and quicker than running power whips from RPPs under the floor, laid in cable trays, then pulled up through floor cut-outs to the IT racks. This was estimated to save 2 days of labor.

The savings with the frame-based approach can be even greater if you factor in the installation of the IT equipment, since IT equipment work including unboxing, de-trashing, installing, and plugging the equipment into racks can all be done in parallel to the pod assembly. 

In contrast, these activities would generally be done upon project completion for the traditional design, since the racks are a necessary part of the construction of traditional containment.

Article by Wendy Torell, Schneider Electric Data Center Blog 

Lenovo DCG moves Knight into A/NZ general manager role
Knight will now relocate to Sydney where he will be tasked with managing and growing the company’s data centre business across A/NZ.
The key to financial institutions’ path to digital dominance
By 2020, about 1.7 megabytes a second of new information will be created for every human being on the planet.
Is Supermicro innocent? 3rd party test finds no malicious hardware
One of the larger scandals within IT circles took place this year with Bloomberg firing shots at Supermicro - now Supermicro is firing back.
Record revenues from servers selling like hot cakes
The relentless demand for data has resulted in another robust quarter for the global server market with impressive growth.
Opinion: Critical data centre operations is just like F1
Schneider's David Gentry believes critical data centre operations share many parallels to a formula 1 race car team.
MulteFire announces industrial IoT network specification
The specification aims to deliver robust wireless network capabilities for Industrial IoT and enterprises.
Google Cloud, Palo Alto Networks extend partnership
Google Cloud and Palo Alto Networks have extended their partnership to include more security features and customer support for all major public clouds.
DigiCert conquers Google's distrust of Symantec certs
“This could have been an extremely disruptive event to online commerce," comments DigiCert CEO John Merrill.